| Pittsburgh, Pennsylvania |
Contract Value: $17.5 Million |
| Light Rail Transit System - Stage I and Stage II |
|
| Contract CY 810, CY 240, and LRS-97-01 |
|
| |
|
|
| Description of Work: |
| CY-240 -Mount Lebanon, Pennsylvania |
| |
Construct 13,950 TF 115# RD - CWR trackage = 62 1/2" track gauge. |
| |
4,450 TF Mount Lebanon Tunnel Direct Fixation trackage - 2% grade. |
| |
Miscellaneous vehicular and pedestrial corssings. |
| |
Signal, communication and electrical catenary work. |
| |
|
| LRS-97-01 - Broadway Avenue Track Renewal |
|
Complete rebuild of 3,800 LF embedded #115 trackwork including demolition of concrete, sub-grade preparation, reinforced concrete trackway with hi-strength grout encapsulated track. |
|
Overhead catenary renewal, rehabilitation and replacement; all work done under single track outage including numerous urban environment restrictions. |
| |